Cost Plan Schedule

The “Cost Plan Schedule” Smart Tool shows how Project costs are distributed over time based on the work Schedule.

See your upcoming financial commitments in advance and plan payments to avoid cash flow gaps.

Сlick “Export”.
Select “Cost plan schedule” as the Schedule format.
Choose whether to display materials in the exported file.
How does it work?
  1. pen any Work Package and go to the “Schedule” tab.
  2. Complete the Schedule by planning the work and material deliveries for the Work Package.
  3. Click “Export” (1).
  4. Select “Cost plan schedule” as the Schedule format (2) and choose whether to display materials in the exported file (3).
  5. Click “Export”. The generated Excel file will be downloaded to your computer.

Use the Cost Plan Schedule to analyze the Project’s expected financial load and plan how much you will need to spend over the coming months.